By Daniel Keeton Updated 5 min read

Yes. An unpaid contractor or supplier can record a mechanic's lien on a Virginia home, and a recorded lien shows up in the buyer's title search. A general contractor can file up to 90 days after the last day of the month of last work, and no later than 90 days after completion (Va. Code § 43-4). At settlement, the seller signs a statement that everyone hired for work in the prior 120 days has been paid, or lists who hasn't (§ 43-13.3). Pay for finished work, keep lien releases and resolve disputes before going under contract.

It can. In Virginia, a contractor or supplier who isn’t paid for work on your home can record a mechanic’s lien against the property, and a recorded lien shows up in the buyer’s title search. A general contractor can file any time after work starts, up to 90 days after the last day of the month they last worked or supplied materials, and no later than 90 days after the job is finished (Va. Code § 43-4). Virginia also requires you, as the seller, to sign a statement at settlement about whether everyone you hired in the last 120 days has been paid (§ 43-13.3). The safe plan is simple: pay for finished work, get it in writing and resolve disputes before you’re under contract.

This is a plain-language summary of Virginia’s mechanics’ lien law (Title 43 of the Code of Virginia), not legal advice. If a lien has been filed or threatened, talk to a Virginia real estate attorney and your settlement agent.

Who can file a lien on a house in Virginia?

People who perform labor or furnish materials worth $150 or more to build, repair or improve a building can have a lien on it, if they perfect it the way the law requires (§ 43-3). For repairs or improvements to an existing house, the lien attaches only if the owner or the owner’s agent ordered or authorized the work.

That group isn’t limited to the company you hired. A subcontractor or supplier can perfect a lien too, but it has to notify the owner of its claim, and the amount is capped at what the owner still owes the general contractor when notice is given (§ 43-7). That’s one reason to keep proof of every payment.

What are the deadlines?

Step Deadline Source
General contractor records a memorandum of lien Any time after work starts, but no later than 90 days from the last day of the month of last work or materials, and no later than 90 days after completion § 43-4
What the memorandum can cover Generally no work or materials more than 150 days before the last day worked, except retainage up to 10% and certain sums not yet due § 43-4
Claimant sues to enforce the lien Within 6 months of recording or 60 days after the work was completed or ended, whichever is later § 43-17

Once a memorandum is recorded and indexed in the circuit court clerk’s office, everyone is deemed to have notice of it (§ 43-4).

A hypothetical to show the timing: you have the deck rebuilt and the contractor’s last day is September 12. Counting 90 days from September 30, the last day of that month, gives December 29, but a filing also can’t come more than 90 days after the job is completed, which here is December 11. If you list in October and settle in November, your whole contract period sits inside the window when an unpaid contractor could still record a lien.

What do you sign at closing?

When you sell a one- or two-family home, you give the buyer (or the lender, on a refinance) a sworn affidavit or a signed statement attested by a witness. It says either that everyone you contracted with for labor or materials on the property in the 120 days before settlement has been paid in full, or it lists anyone unpaid with their name, address and the amount owed or claimed (§ 43-13.3). A willful material misrepresentation that causes a loss to a lender, title company or buyer is a Class 3 misdemeanor.

If you’re a builder, developer or contractor selling a home you own and improved, a stricter version applies, and willful failures or misstatements can be a felony (§ 43-13.2).

Tell your settlement agent about any recent work early. It’s much easier to sort out a final invoice in week one of a contract than the day before closing. Our guide to what happens at a Virginia home closing walks through the rest of settlement.

What does a building permit have to do with it?

For one- and two-family homes, the building permit must be posted on the property, and it can name a mechanics’ lien agent (§ 43-4.01). When an agent is named, people furnishing labor or materials are supposed to notify that agent within 30 days of starting. If they don’t, their lien is limited to work done on or after the date they finally give notice. If you’re planning a permitted project before you sell, ask about naming a lien agent when the permit is issued.

How do you keep a lien from holding up your sale?

  • Finish and pay before you list, when you can. Projects that end well before settlement are outside the 120-day statement and closer to the end of a contractor’s filing window.
  • Get paperwork with each payment. Keep invoices, proof of payment and a written lien waiver or release from the contractor, and ask the contractor for releases from major subcontractors and suppliers.
  • Don’t plan to “settle up after closing.” An open bill or a disputed final invoice is exactly what the 120-day statement asks about.
  • If something is already recorded, call your settlement agent and an attorney right away. A recorded lien usually has to be paid, released or otherwise resolved before the buyer’s title insurer and lender will close. A lien claimant who knowingly includes work not performed or materials not furnished, with intent to mislead, forfeits the lien (§ 43-23.1), but that’s a question for a lawyer, not a reason to ignore a filing.

If you’re deciding which projects are worth doing at all, read should I make repairs before listing my home. When I help sellers plan pre-listing work, I ask about the payment schedule and the finish date before the paint color, because those two things decide whether the work helps the sale or complicates it.

What about buyers?

If you’re buying, your title search will show recorded liens, and your title insurance options are worth discussing with your settlement agent, especially when the seller recently renovated. Ask the listing agent what work was done, when, and whether it’s paid for.

What’s the next step?

If you’ve done work on your home and you’re thinking about selling, Daniel and the Keeton & Co team can help you plan the timing so the paperwork is in order before you list. Talk to us about selling or contact our team.

No pressure, no spam

Talk to a Keeton & Co agent

A licensed agent reaches out within 5 minutes during business hours, from (804) 556-1228.

By submitting, you agree that Keeton & Co Real Estate and its agents may call and text you at the number you provided about your real estate inquiry, including by automated means and AI-generated or prerecorded voice. Consent is not a condition of purchase. Msg & data rates may apply. Reply STOP to opt out. Privacy Policy

More on selling